A. 2.2.1.5 | Pembuatan 1 m2 kantor sementara lantai plesteran | ||||||
Tenaga | |||||||
Pekerja | L.01 | OH | 2,000 | - | |||
Tukang Kayu | L.02 | OH | 2,000 | - | |||
Tukang Batu | L.02 | OH | 1,000 | - | |||
Kepala Tukang | L.03 | OH | 0,300 | - | |||
Mandor | L.04 | OH | 0,050 | - | |||
Jumlah (1) | - | ||||||
Bahan | |||||||
Dolken kayu 8-10/400 cm | Btg | 1,250 | - | ||||
Kayu | m3 | 0,180 | - | ||||
Paku biasa | kg | 0,080 | - | ||||
Besi strip | kg | 1,100 | - | ||||
Semen portland | kg | 35,000 | - | ||||
Pasir pasang | m3 | 0,150 | - | ||||
Pasir beton | m3 | 0,100 | - | ||||
Koral beton | m3 | 0,150 | - | ||||
Bata merah | bh | 30,000 | - | ||||
Seng plat | lbr | 0,250 | - | ||||
Jendela naco | bh | 0,200 | - | ||||
Kaca polos | m2 | 0,080 | - | ||||
Kunci tanam | bh | 0,150 | - | ||||
Plywood 4mm | lbr | 0,060 | - | ||||
Jumlah (2) | - | ||||||
Jumlah (1) + (2) | - | ||||||
Overhead & Profit (15%) | - | ||||||
Jumlah Total | - |